11th PRIME Plenary Meeting, Brussels, 16 November … · An inquiry by DB , the German Armed Forces...
Transcript of 11th PRIME Plenary Meeting, Brussels, 16 November … · An inquiry by DB , the German Armed Forces...
Hinweis:
Für externe Präsentationen bitte immer eine Titelfolie mit der Ressort-Farbe verwenden.
11th PRIME Plenary Meeting, Brussels, 16 November 2017
State of Play: Review of Rastatt disruption and
first ideas for contingency plans
DB Netz AG | Bettina Wunsch-Semmler | 2017-11-16
Agenda
DB Netz AG | Bettina Wunsch-Semmler 2
1.
2.
3.
Rastatt incident
Rerouting of rail freight
Review
On August 12th a lowering of tracks happened south of
Rastatt in the framework of tunnel construction works
DB Netz AG | Bettina Wunsch-Semmler 3
As a consequence the route Karlsruhe - Basel had to be closed immediately and completely between
Rastatt and Baden-Baden after the incident.
Affected area
Target shaft
Tunnelling machine
Shield
East tunnel
West tunnel
Southern
trough
structure
The first actions on the damaged railway section
involved stabilizing the tunnel construction site
DB Netz AG | Bettina Wunsch-Semmler
Immediate
stabilization of the
damaged tunnel
section
Since 17 August
2017, a concrete
grafting separates
the damaged part
from the intact part
of the 4,000 meter
long tunnel
On 25 August 2017,
the filling of the
tunnel was
completed and the
precautionary
evacuated residents
returned to their
homes
4
The damaged
tunnel section was
stabilized by filling it
with around 10,500
cubic meters of
concrete
Cave in
Damage area
Ground level
Shield
Rhine valley railways Drilling
concrete-grafting
East tunnel
West tunnel
Tracks
Gym
Icing area
Support for auxiliary bridge
Cave in area
The installation of provisional bridges was not possible for
several reasons and was discarded as a solution
DB Netz AG | Bettina Wunsch-Semmler 5
Deep foundation (3 - 6 m) can
only be statically implemented
outside the icing area, which
means that 2 auxiliary bridges
with an overlap length of 120 m
are necessary
An inquiry by DB , the German
Armed Forces and the NATO
member countries was negative
The time required for the
necessary track clearance,
installation and foundation is
greater than for the selected
cast-in-place concrete
Due to its surface-supporting
effect, the cast-in-place
concrete does not require a
deep foundation and can
therefore be shorter
Excursus
To restore operation on the high-frequency Rhine
valley railway a concrete superstructure was built
DB Netz AG | Bettina Wunsch-Semmler 6
For the secure and
lasting restoration of
the track a concrete
slab above the
tunnel and below
the existing
superstructure was
build
After production of
the "concrete floor"
the laying of gravel,
rails and the
installation of the
signal technology
began
On 2 October 2017
the Rhine valley
railway was back in
operation – five
days earlier than
originally planned
As preventive
measure a second
concrete slab was
build above the
second tunnel tube
to stabilize the
ground further
Rhine valley railways
Ground level
Shield
Construction of the concrete slab
backfilling
Agenda
DB Netz AG | Bettina Wunsch-Semmler 7
1.
2.
3.
Rastatt incident
Rerouting of rail freight
Review
DB Netz AG | Bettina Wunsch-Semmler 8
Damaged
area
I a Gäubahn (A), I b Neckar-Alb (B)
I c Südbahn
I d Konstanz Via Kufstein to II a Brenner, via Salzburg to II a Tauern
RFC North-Sea Mediterranean
III b Forbach-Kehl
III c Lauterbourg
II a Brenner
II a Tauern
Communication of the pre-defined diversion routes
started already on 13 August 2017
On average 30 % of the offered capacity was used
DB Netz AG | Bettina Wunsch-Semmler 9
IIIc
Lauterbourg
9% IIIb
Forbach-Kehl 13%
IIb
Tauern 3%
Ic
Südbahn
10%
Ib
Neckar-Alb 13%
Ia
Gäubahn
14%
11%
IIa
Brenner
27% Id
Konstanz
Share of path offer on the diversion routes
100 % = 7,888 paths = approx. 155 paths / day Path usage on diversion routes
24
%
IIIb
Forb
ach
-Kehl
23%
IIb
Ta
uern
IIa
Bre
nner
7%
100%
IIIc
La
ute
rbourg
Id
Konsta
nz
Ic
Südb
ahn
4
7%
Ib
Necka
r-A
lb
48%
Ia
Gäub
ahn
84
%
Used
capacity
Unused
capacity
Ø 30 %
The capacity offer was only possible due to the good cooperation with neighbouring IMs, the RFC
Rhine-Alpine, North Sea-Mediterranean and ScanMed. Remark: Figures represent only information available to DB Netz; Trains deviated completely around Germany are missing
DB Netz took measures to reduce the impact of
Rastatt and to improve the use of diversion routes
DB Netz AG | Bettina Wunsch-Semmler 10
Capacity increase by
additional measures
Shifting of planned works and
the reduction of track
possessions
Reduction of passenger
transport services to increase
capacity for rail freight
Additional staff in the
network control centre, the
operations control centre in
Karlsruhe and signal tower in
Singen
Allocation of additional
sidings in Singen and Kehl
Crisis Management
Communication
Weekly telephone
conferences on CEO-level of
the countries involved
Daily telephone conferences
on working level between the
concerned RUs, IMs and DB
Netz
Support of RUs
operations
Free of charge provision of 7
diesel hauling-locomotives for
non electrified line Tübingen-
Horb
Support of the RUs for setting
up a pool of train drivers
Additional shunting staff in
the train station of Singen for
support of operation
After re-opening of the
Gäubahn:
provision of a shunting- and
pushing locomotive (incl.
shunting staff) in Singen
Nonetheless capacity on diversion routes could not be
used fully due to several restricting factors for the RUs
DB Netz AG | Bettina Wunsch-Semmler 11
Resources of RUs
Operating on diversion routes
requires additional resources
due longer turnaround cycles:
– lack of train drivers
– lack of locomotives
Infrastructure
Line parameters on diversion
routes differ from the ones on
the Rhine valley railway, e.g.
in regard to
– clearance gauge and
– length of stable and
passing sidings
Interoperability
Train drivers could not be
assigned on certain routes
due to
– missing route knowledge
and
– required operational
language
Available locomotives where
not always certified in certain
countries on the diversion
routes
The lesson is that in general the use of diversion routes in case of incidents must be improved by
harmonizing line parameters and increased cross-border interoperability
On 02.10.2017 traffic on the Rhine valley railway
restarted smoothly and volumes are on a normal level
DB Netz AG | Bettina Wunsch-Semmler 12
77
127
160
177
157
138
7274
91
130
169
191
152
134
66
0
50
100
150
2001,0
0,3
0,9
0,4
0,5
0,7
0,8
0,6
0,0
0,1
0,2
08.10.2017 02.10.2017 01.10.2017 07.10.2017 06.10.2017 05.10.2017 04.10.2017 03.10.2017
Operated trains (incl. ad-hoc traffic) Annual Timetable (Bank holiday on 3 Oct) Remark: Low planned traffic volumes until 3 Oct due to bank holiday
Agenda
DB Netz AG | Bettina Wunsch-Semmler 13
1.
2.
3.
Rastatt incident
Rerouting of rail freight
Review
Since the reopening of the line an intensive review
process is ongoing
DB Netz AG | Bettina Wunsch-Semmler 14
Gathering feedback
from relevant
stakeholders
Establishment of
an action list
Starting projects at
IMs/RFCs and
other stakeholders
Presentation of
first findings and
further process
Time: until November
2017
Review surveys,
workshops/
discussions with
internal and external
stakeholders
Time: until December
2017
Drawing conclusions
from the feedback
and developing an
action list
Time: until February
2018
For most topics still to
be defined, few projects
already starting after
feedback discussions
Time: until March
2018
Ongoing process,
many requests for
presentations and
discussions with all
stakeholders
Ongoing process
First lessons learned have already been identified
DB Netz AG | Bettina Wunsch-Semmler
„You never want a serious crisis to go to waste. And what I mean by that is an opportunity to do things that you
think you could not do before.”-Rahm Emanuel
DB Netz and RFC Rhine-Alpine will develop/propose measures in close cooperation with the relevant
stakeholders (IMs, RUs, RFCs, etc.).
15
Agree on international crisis management process supported by RFCs
Agree on process/check-list for communication supported by RFCs
Develop multi-national re-routing overview for RFCs
Define clear capacity allocation rules in case of incidents
1. Improving multi-national crisis management / contingency plan
Increase capacity on diversionary lines by improving the infrastructure
Intensify coordination of works along rail freight corridors in cooperation with customers
3. Improve infrastructure and international coordination of works
Harmonizing of operational rules and authorisation conditions (in case of incidents)
Implementation of a second operating language
2. Developing frame conditions for a flexible production in rail freight
Contingency plans for multi-national incidents should
include several elements – first ideas
DB Netz AG | Bettina Wunsch-Semmler 16
Explanations
International incident
management
Criteria for major international incident:
Duration: proposal > 5 days
High impact on international rail freight
Process proposal:
RFCs coordinate telcos/cooperation between heads of incident
management of involved IMs
Communication in case
of multi-national
incidents
Re-routing overview
Capacity allocation
rules
Process proposal:
RFCs coordinate telcos of heads of communication of involved IMs
Communication of stakeholders by each involved IM based on agreed
check-list for external communication
RFCs also inform their specific stakeholders
Overview of diversionary routes for each RFC with information on
infrastructure parameters, capacity indication, restrictions at RUs
Clear rules to be defined/agreed by Regulatory Bodies in Europe
1
2
3
4
We experience a high interest in the lessons learned
from all kinds of stakeholders
DB Netz AG | Bettina Wunsch-Semmler 17
DB Netz and RFC Rhine-Alpine already started a review process to gather feedback from all
stakeholders. This feedback will be incorporated in the lessons learned and a consecutive action plan.
The timeline is not yet finalized but will include the following dates pre-set by the stakeholders:
11-12 October Busto Arsizio Executive Board und Railway Undertakings/Terminal Advisory Group (RAG/TAG) of RFC Rhine-Alpine
16 October Brussels Forum of TEN CNC Rhine-Alpine
25 October Verona Railway Undertakings/Terminal Advisory Group (RAG/TAG) of RFC Scandinavian-Mediterranean
26 October 2017 RU Dialogue
9-10 November Brussels SERAC and NExBo
16 November/ 17 January 2018 PRIME
29 November Rome Management Board of RFC Rhine-Alpine
06 December Düsseldorf HUPAC conference “Rastatt disaster: Never again”
07 December Vienna Annual Rail Freight Day of EU and RNE
11-12 December Frankfurt Executive Board of RFC Rhine-Alpine
23 January 2018 Frankfurt SBB Infrastruktur / DB Netz AG Management Board
21 February 2018 SBB / DB CEO Meeting
Hinweis:
„Vielen Dank für Ihre Aufmerksamkeit“ kann auch durch ein anderes Abschlusszitat oder eine Botschaft ersetzt werden.
Thank you for your attention