Unternehmung WENDELSTEIN 7-X Max-Planck- Institut für Plasmaphysik Torsten Bräuer1CMSC, Charlotte,...
-
Upload
natalie-torres -
Category
Documents
-
view
216 -
download
2
Transcript of Unternehmung WENDELSTEIN 7-X Max-Planck- Institut für Plasmaphysik Torsten Bräuer1CMSC, Charlotte,...
Unternehmung
WENDELSTEIN 7-X
Max-Planck-Institut für Plasmaphysik
Torsten Bräuer 1CMSC, Charlotte, July 2008
High geometric precision in the construction of the
WENDELSTEIN 7-X fusion experiment
T. Bräuer
Max-Planck-Institut für PlasmaphysikUnternehmung WENDELSTEIN 7-X
D-17491 Greifswald, Wendelsteinstraße 1
Content: Fusion basics and assembly strategy
Second order datum point system on components
Survey of first magnet half module
Conclusion, outlook
Fusion Experiment WENDELSTEIN 7-X
Unternehmung
WENDELSTEIN 7-X
Max-Planck-Institut für Plasmaphysik
Torsten Bräuer 2CMSC, Charlotte, July 2008
WENDELSTEIN 7-X is a fusion experiment !
Physical Aim:
• Prove of the stellarator principle as a realistic concept for a future power plants
• but no break even, no Tritium
• Control of a plasma at very high temperatures of 100 Mio Kelvin
• Quasi stationary operation
Technical aim:
• Construction of the device under industrial like conditions
• Very tight collaboration with manufacturers
Creation of a very strong, very precise magnet field with a relative accuracy of 1...2·10-4
p p D e
D p 3 He
3He 3
He 4He 2p
WENDELSTEIN 7-X: fusion basics
Unternehmung
WENDELSTEIN 7-X
Max-Planck-Institut für Plasmaphysik
Torsten Bräuer 3CMSC, Charlotte, July 2008
Design scheme of W7-X• Main dimensions of W7-X
• Main radius:5.5m
• High: 5.5m
• Mass:725t
• 50 non planar coils (NPC)
(Ø 3.0 m, m = 5 t)
• 20 planar coils (PLC)
(Ø 3.5 m, m = 2 t)
• Coil support structure (CSS)
• Plasma vessel (PV)
• Outer vessel (OV)
WENDELSTEIN 7-X: assembly strategy
• Fivefold symmetry of torus
• Flip symmetry of a module
Unternehmung
WENDELSTEIN 7-X
Max-Planck-Institut für Plasmaphysik
Torsten Bräuer 4CMSC, Charlotte, July 2008
Fivefold and flip symmetry:
Fivefold symmetry:
• 5 identical modules with 10 NPC and 4 PLC, CSS, PV
Flip symmetry:
• 2 flip symmetric half modules per module
• 5 NPC und 2 PLC per half module
• Flip symmetric half modules of CSS
• Flip symmetric half modules of PV
WENDELSTEIN 7-X: assembly strategy
Unternehmung
WENDELSTEIN 7-X
Max-Planck-Institut für Plasmaphysik
Torsten Bräuer 5CMSC, Charlotte, July 2008
Steps of half module assembly:
1. Adjustment of coilsAccuracy requirements: 0.5 … 1.5 mm
2. Adjustment of coil support structure Accuracy requirements: 1.0 … 1.5 mm
WENDELSTEIN 7-X: assembly strategy
Unternehmung
WENDELSTEIN 7-X
Max-Planck-Institut für Plasmaphysik
Torsten Bräuer 6CMSC, Charlotte, July 2008
Module and torus assembly:
3. Two half modules are jointed together
4. Module is lowered in half shell of outer vessel and adjusted to final position
WENDELSTEIN 7-X: assembly strategy
Unternehmung
WENDELSTEIN 7-X
Max-Planck-Institut für Plasmaphysik
Torsten Bräuer 7CMSC, Charlotte, July 2008
Adjustment of components:
• mainly done by Laser-Tracker (LTD)
• 6 … 12 datum points per component
• Adjustment residual: 0.5 … 1.5 mm
• Survey accuracy: 0.2 … 0.3 mm
Final surveys and documentation:
• Mainly done by photogrammetry
• Short survey time
• Flexible lines of sight and camera positions possible
• Survey accuracy: 0.2 … 0.4 mm
Access to datum points becomes more and more difficult with progress of assembly due to using fitted holes for assembly purposes and blocking of lines of sight by components and staff folders
Creation of a second order datum point system with a high number of points is necessary !
WENDELSTEIN 7-X: assembly strategy
Unternehmung
WENDELSTEIN 7-X
Max-Planck-Institut für Plasmaphysik
Torsten Bräuer 8CMSC, Charlotte, July 2008
WENDELSTEIN 7-X: second order datum points
Half module of support structure:
Size [m]: 1,5 x 2,5 x 2,5; weight 5 t
Creation of a second order datum point system for photogrammetry on the components
Non planar coil: size [m]: 2,5 x1,5 x 3,5; weight 5.5 t
• Usually 12…20 original datum points per component
• Installation of additional 200 second order points for photogrammetry
• Roughly 200…300 pictures necessary
• Roughly 1day
Unternehmung
WENDELSTEIN 7-X
Max-Planck-Institut für Plasmaphysik
Torsten Bräuer 9CMSC, Charlotte, July 2008
Creation of a second order datum point system for photogrammetry on a coil sticky targets
on the coil
Support P1 Stand foot 2
Stand foot 1
Support M1 a. 2
Aux. point 3
Coil support 1 a. 2
Ref. points
3.5m
Coil with original datum points
Feature targets for using in fitted holes, i. e. original datum points
Usually 12…15 original datum points per coil
200 new points per coil
Comparison of photogrammetry and Laser-Tracker at 15 datum points
WENDELSTEIN 7-X: second order datum points
Unternehmung
WENDELSTEIN 7-X
Max-Planck-Institut für Plasmaphysik
Torsten Bräuer 10CMSC, Charlotte, July 2008
repeatability accuracy of new points
0 1
16
103
52
34
111 3 0 0
0
20
40
60
80
100
120
10 20 30 40 50 60 70 80 90 100 110
RMS per point [µm]
nu
mb
er
of
po
ints Number of points: 221
Number of surveys: 6Mean RMS: 42µm
Conditions:• No air condition• Different operators• For each survey a new set up of scale bars and
coded targets• Removing and replacing targets of datum holes
32%68%
Accuracy analysis of second order datum points:
• LTD repeatability accuracy (σ): 0.0625 mm
WENDELSTEIN 7-X: second order datum points
Result:Under real conditions the second order datum points show additional but acceptable uncertainties and can be used in later surveys
comparison of photogrammetry and LTD
0
2
3
6
4
0 00
1
2
3
4
5
6
7
0.05 0.10 0.15 0.20 0.25 0.30 0.35deviation per point [mm]
num
ber o
f poi
nts
Number of points: 15RMS: 0.17 mm
Unternehmung
WENDELSTEIN 7-X
Max-Planck-Institut für Plasmaphysik
Torsten Bräuer 11CMSC, Charlotte, July 2008
WENDELSTEIN 7-X: Survey of first magnet half module
Situation for survey of magnet half module:
• Two assembly stands next to each other
• Workflow in work shop is ongoing (crane, transport, …)
• No air condition
• Volume of half module 4 x 5 x 4 m³
• Max. high over ground: 6m
• Lots of fixing structures, platforms …
Unternehmung
WENDELSTEIN 7-X
Max-Planck-Institut für Plasmaphysik
Torsten Bräuer 12CMSC, Charlotte, July 2008
WENDELSTEIN 7-X: Survey of first magnet half module
Situation for survey of magnet half module:
Access to the coils is blocked by:
• Machine table at bottom
• Support structure at inner side
• Fixing structures at back, left and right
Unternehmung
WENDELSTEIN 7-X
Max-Planck-Institut für Plasmaphysik
Torsten Bräuer 13CMSC, Charlotte, July 2008
WENDELSTEIN 7-X: Survey of first magnet half module
Results of photogrammetry survey: accessibility of datum points
• 5 independent surveys
• Up to 750 pictures per survey
First order datum points:
• Total number at all coils: 152
• Accessible by photogrammetry: 53
• Accessible by Laser-Tracker: 57 (only by using of T-Probe)
Second order points:
• Total number at all coils: 1544
• Accessible 780
Accessibility of datum points of amagnet half module
7
6
10 10
3
9
88
5
9
11
8
9
7
0
2
4
6
8
10
12
14
16
AAB13 AAB17 AAB22 AAB45 AAB51 AAC13 AAC51
coils
nu
mb
er o
f p
oin
ts
Phg
LTD
sec. order Phg *10
Unternehmung
WENDELSTEIN 7-X
Max-Planck-Institut für Plasmaphysik
Torsten Bräuer 14CMSC, Charlotte, July 2008
comparision: actual - nominal coil position
0.0
0.2
0.4
0.6
0.8
1.0
1.2
1.4
first order datum points of coils
devi
atio
n [m
m]
AAB13 AAB22 AAB45 AAB51 AAC13 AAC51AAB17
WENDELSTEIN 7-X: Survey of first magnet half module
Results of photogrammetry survey: comparison of actual and nominal coil position
• Required adjustment tolerance: 1.5 mm
• Maximum deviation: 1.3 mm
• Est. repeatability accuracy of survey (68%): 0.25 mm
• Cross check with Laser-Tracker survey shows similar results (see below)
• Actual coil positions meet the tolerance requirements
Unternehmung
WENDELSTEIN 7-X
Max-Planck-Institut für Plasmaphysik
Torsten Bräuer 15CMSC, Charlotte, July 2008
repeatability accuracy
11
364
539
202
56
16 6 4 0 00
100
200
300
400
500
600
0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.8 0.9 1
RMS per point
nu
mb
er o
f p
oin
ts
Repeatability accuracy analysis:
32%68%
Number of points: 1198Mean RMS: 0.25 mm
WENDELSTEIN 7-X: Survey of first magnet half module
• Number of surveys: 5
• Duration of all 5 surveys: 1d
• 2 operators
• 1 camera
• In all surveys the same set up of scale bares and coded targets
• No air condition
• Ongoing workflow in workshop
Unternehmung
WENDELSTEIN 7-X
Max-Planck-Institut für Plasmaphysik
Torsten Bräuer 16CMSC, Charlotte, July 2008
• One Laser-Tracker survey
• (Laser-Tracker used with T-Probe)
• Duration: 1d
• Maximum deviation of a coil measured by Laser-Tracker: 1.41 mm
⇨Meets the tolerance requirement
• Average of 5 photogrammetry surveys
• Transformation of photogrammetry to Laser-Tracker survey
Cross check with Laser-Tracker:
WENDELSTEIN 7-X: Survey of first magnet half module
comparison of photogrammetry and Laser-Tracker
3
2
5
3
2
5 5
3
1
0 0 00
1
2
3
4
5
6
0.05 0.1 0.15 0.2 0.25 0.3 0.35 0.4 0.45 0.5 0.55 0.6
deviation [mm]
nu
mb
er o
f p
oin
ts
number of points: 29Mean deviation: 0.22 mmRMS: 0.25 mm
Unternehmung
WENDELSTEIN 7-X
Max-Planck-Institut für Plasmaphysik
Torsten Bräuer 17CMSC, Charlotte, July 2008
WENDELSTEIN 7-X: Conclusion, outlook
Conclusion, outlook :
• Coils of fist magnet half module have been assembled inside required tolerance!
• Assembly methods have been proofed and can be used for future modules
• Assembly is feasible under industrial like conditions, especially under fast rate of construction
• Photogrammetry has been proofed as a reliable and fast survey technique for final surveys
• Accessibility can be improved by a second order datum point system for photogrammetry, especially for the next assembly steps: module assembly
assembly of torus
• Second order datum points show an acceptable increase of uncertainty
• New generation of cameras will be tested to reduce survey time and improve accuracy
The experiment WENDELSTEIN 7-X will go intooperation in 2014 !