SIA, Swiss Society of Engineers and Architects s i a Contract for architectural services No. 1002 2003 Regarding the project: Andermatt Tourism Resort granted Name / Address: (Client) Andermatt Swiss Alps S.A. Gotthad Street 2 6490 Andermatt The architect (Consultant) 1 Name / Address: Andrea Sebastiano Freda Via delle Fomaci 29 1-00165 Roma The order described in this contract Order for: Preliminary design, development, approval procedures, design leadership for Zone 4 Key No. 4/2 1 The Consultant is a member * of the SIA, Swiss Society of Engineers and Architects; Section: other professional associations (do not use only abbreviations): She / he is registered in the Swiss Register 1 ****** . © sia / dg – informatik 1002-2003 No. 2387

Transcript of Zutreffendes ankreuzen und wenn nötig ergänzen

Page 1: Zutreffendes ankreuzen und wenn nötig ergänzen

SIA, Swiss Society of Engineers and Architects

s i aContract for architectural services No. 1002

2003

Regarding the project:

Andermatt Tourism Resort

granted

Name / Address: (Client)

Andermatt Swiss Alps S.A.Gotthad Street 26490 Andermatt

The architect (Consultant)1

Name / Address:

Andrea Sebastiano FredaVia delle Fomaci 291-00165 Roma

The order described in this contract Order for:

Preliminary design, development, approval procedures, design leadership for Zone 4

Key No. 4/2

1 The Consultant is a member

* of the SIA, Swiss Society of Engineers and Architects; Section:

other professional associations (do not use only abbreviations):

She / he is registered in the Swiss Register

* A of Architects

B of Architects

C of Technicians

* Check all that apply and add if necessary

1 ****** . © sia / dg – informatik 1002-2003 No. 2387

Page 2: Zutreffendes ankreuzen und wenn nötig ergänzen

1 contract components and their priority in case of contradictions

1 * This contract document and any attachments according to Directory P. 11

2 * The End of the Consultant with the service description of : ,

both adjusted on : ,

3 * The task description of the project-related provisions of the Client of : ,

both adjusted on : ,

4 * The SIA published statistical values Z1 and Z2 for the calculation of the average hourly expense (Tm)

* Valid until end of contract

Valid until

5 * The Regulation SIA 102, 2003 edition

Simply reflect the definitions and Art. 1 of the Regulation SIA 102, 2003 edition although subject to the provisions of this contract document, According to, in particular those in paragraph 14.

6 *

7 *

In case of doubt the scheme in part of the agreement with the lower order numbers according to the above list shall prevail. Where there are conflicts within the same part of the agreement then the later document shall prevail over the elder.

For the meaning of the terms used, Regulation SIA 102 (2003) is authoritative.

* Check all that apply and add if necessaryDate and signature symbol of the Parties

2 ****** . © sia / dg – informatik 1002-2003 No. 2387

Page 3: Zutreffendes ankreuzen und wenn nötig ergänzen

Services of the officers and their remuneration

2.1 Services

The achievements of the representative(s)

are available from the / of the Consultant as of: (adjusted on: ) described

include the following basic benefits according to Article 4 of the Rule SIA 102 (2003)

31 PreliminaryStudy of possible solutions and rough estimate of construction costs 2.0 %Preliminary design and cost estimate 4.0 % 6.00%

32 Construction project Construction project 13.0 %Detailed studies 4.0 %Estimate 0.0 % 17.0 %

33 Approval Procedures Approval Procedures 1.5 %

41 Request for Tender, Open- comparison, Invitation

Invitation Plans 0.0 %

Award of Procurement 0.0 % 0.0 %

51 Construction Plans Construction Plans 0.0 %Contracts for Work 0.0 % 0.0 %

52 Construction Design management 6.0 %Construction management and cost control 0.0 % 6.0 %

53 Commissioning, Final Commissioning 0.0 % Documentation about the building

work 0.0 %Management of warranty work 0.0 %Final Settlement 0.0 % 0.0 %

Total Basic Services 30.0 %

* Include the following special services agreed upon in accordance with Article 3.3.4 and Article 4 of the Rules SIA 102 (2003):

* Be agreed as follows:

Account must be issued each separate per QGB-Zone and per Key No.The following details must be confirmed in accounts:QGB-Zone 4f / Project Name: Zone 4 f; Key 4 f2Project Number: Z4F_02.000 /BKP No.: 291 Architecture Cost Center: 514470 / Account No.: 14471 / VA-No.: B504In the preliminary phase account the rough estimate of Construction costs and the cost estimate.

3 ****** . © sia / dg – informatik 1002-2003 No. 2387

Page 4: Zutreffendes ankreuzen und wenn nötig ergänzen

* Check all that apply and add if necessaryDate and signature symbol of the Parties

4 ****** . © sia / dg – informatik 1002-2003 No. 2387

Page 5: Zutreffendes ankreuzen und wenn nötig ergänzen

2.2 Basics of fee calculation

- * with payment to the construction costs pursuant to Annex 6

The calculation of the fee for the construction costs made in accordance with Article 7.2 – 7.5 of The Regulation SIA 102 (2003) because

* The final settlement

The cost estimate

According to the following costs:

Here, construction cost shall be calculated from the agreed fees. Also in determining the final fee in accordance with this final statement is expected by the factors "Average time in hours" (Tm) and job-specific "forecast time" (Tp) and not with the actual hours required for the project.

The estimated expenditure-determining construction costs are: CHF

Expense supplement in% for conversions:

according to building category: with the degree of difficulty n =

Power fraction q in %: 30 %

Adjustment factor r:

With the different value of 1.0 of factor r the following flows shall be considered:

Team Factor i:

Factors derived from the value 1.0 are to be included in the fees (Annex 6).

Justification for the deviation from the value i = 1.0:

* Check all that apply and add if necessaryDate and signature symbol of the Parties

5 ****** . © sia / dg – informatik 1002-2003 No. 2387

Page 6: Zutreffendes ankreuzen und wenn nötig ergänzen

Factor for special services s:

Factors derived from the value 1.0 are to be included in the fees (Annex 6).

With different values of 1.0 of the factor s the following special services will be considered:

- * For payment after the time

The calculation of the fee based on the time

* Upon qualifying categories (significant fee rates according to Annex 4)

for salaries, with the following additional factor:

for average hourly rates with the factor a requirement

for the phase 31 =

32 =

33 =

41 =

51 =

52 =

53 =

and the average hourly-fee h = CHF

* For a fixed fee The fixed fee is agreed as follows * Flat (there is no adjustment for inflation) * Global (with adjustment for inflation)

* Check all that apply and add if necessaryDate and signature symbol of the Parties

6 ****** . © sia / dg – informatik 1002-2003 No. 2387

Page 7: Zutreffendes ankreuzen und wenn nötig ergänzen

2.3 Nature and level of remuneration

The client pays according to the contract agreed for the following services and their outcomes such as:

General Description of the services Fee estimate in CHF Fixed fee in CHFfor construction

costsby time

Basic services:See Point 14

Especially agreed services:See Point 14

Total architect's fee (VAT excluded):Plus VAT till the time, from the time 7.60 %Total architect's fee (VAT included):

* Calculation of fees according to Annex 6

3 Payment of fees and costs of third-party services

The payments made:

Nature of the charges and third-party services:

* in percent

The total of fees

* on a time

Estimation in CHF * as a fixed price

in CHF

* inclusive * global

Basic services:See Point 14

Traveling TimeTravel expenses

Total (VAT excluded):Plus VAT till the time, from the time 7.60 %Total (VAT included):

7 ****** . © sia / dg – informatik 1002-2003 No. 2387

Page 8: Zutreffendes ankreuzen und wenn nötig ergänzen

* Check all that apply and add if necessaryDate and signature symbol of the Parties

8 ****** . © sia / dg – informatik 1002-2003 No. 2387

Page 9: Zutreffendes ankreuzen und wenn nötig ergänzen

4 Fees not limited to definite benefits

Benefits in respect of the contract can not yet be conclusively defined are denoted below:

On the content and scope of these services, the contracting parties shall agree before their execution.

The fees are calculated

* After the time according to projections in the supplement

5 Adjustment of allowances for inflation

Fees for the construction costs, professional fees for the time and Global fees are adjusted for inflation according to the following agreement:

There is no adjustment for Inflation

Reimbursement of incidental costs and costs of third-party services are adjusted for inflation according to the following agreement:

There is no adjustment for Inflation

6 Payments

The Payments will be made

* Based on periodic billing by consultant for services and accrued expenses and costs of third-party services.

Overdue payments made within days of billing.

* According to supplement payment in Annex 5. Payments will be made on the agreed date.

* Check all that apply and add if necessaryDate and signature symbol of the Parties

9 ****** . © sia / dg – informatik 1002-2003 No. 2387

Page 10: Zutreffendes ankreuzen und wenn nötig ergänzen

7 Accuracy of cost information

The Consultant keeps the cost information following accuracies:

* according to Article 4 of the Regulations SIA 102 (2003)Preliminary cost estimates for ± 15%Estimate ± 10%

* according to the agreement in point 14

8 dates and deadlines

* Proposed dates and deadlines:

Andermatt Swiss Alps SA has the right to present any agreed services every time to initiate and / or time to terminate or compensation. Non-induced benefits are not paid:

There are, moreover, from the following time limits triggering of the services provided by Andermatt Swiss Alps SA

Preliminary 8 weeksPreliminary to Project Seeking: 18 weeksProject Seeking to completion of tender documents: 12 weeksAward procedures: 8 weeksAward to construction 6 weeks

* The determining factor is the list of term of the dates and deadlines in Annex 1

9 Project Organization

* Project organization (involved in the project partners and their contractual relationships):

As established by Andermatt Swiss Alps SA

* The project's partners and their contractual relationships are described in Annex 2.

* Check all that apply and add if necessaryDate and signature symbol of the Parties

10 ****** . © sia / dg – informatik 1002-2003 No. 2387

Page 11: Zutreffendes ankreuzen und wenn nötig ergänzen

10 Data sharing and data backup

* Data sharing and data backup:

Under the previous contractual arrangements and the recent indications of Andermatt Swiss Alps SA (Particularly CAD Convention as of May 2008)

.

* The provisions for data sharing and data backup are recorded in the supplement.

11 Representation and authority

The Consultant shall, unless the client has no significant scheduling or financial disadvantages accrue interest and value

in each case the amount of: CHF 0 (excl. VAT)

and in total the amount of: CHF 0 (excl. VAT) not exceeding

authorized under the contract for the following acts on behalf of the client

* make statements and amendments to contracts with third parties

recognize and take services of third parties

give instructions to third parties

Generally, the Consultant shall be authorized

* to negotiate with authorities and send requests thereto

12 Insurance

The Consultant shall be insured under

* professional liability insurance

* Syndicate Insurance

Cover for personal injury, property damage, together: CHF

Coverage for damage to buildings: CHF

Insurance Company: Policy No.:

* Check all that apply and add if necessary

11 ****** . © sia / dg – informatik 1002-2003 No. 2387

Page 12: Zutreffendes ankreuzen und wenn nötig ergänzen

Date and signature symbol of the Parties

12 ****** . © sia / dg – informatik 1002-2003 No. 2387

Page 13: Zutreffendes ankreuzen und wenn nötig ergänzen

13 Dispute settlement and applicable law

13.1 Mediation

* Mediation in a dispute shall be performed before referral to a court

* As mediator / mediator is used:

* The mediator / mediator is determined, if necessary

13.2 Jurisdiction

The ordinary courts are responsible beinbg at the registered office / residence of

* The Consultant

* The Client

*

* The responsible is an arbitration court in accordance with Directive 150 SIA

13.3 Applicable Law

For all questions relating to this contract by Swiss law.

14 Special arrangements

The following special arrangements shall go in all cases before any conflicting provisions in this contract document and its supplements.

This contract includes the power under section 2.1 hievor lungs. There is no right of / the Representative on repeat business. The parties are free to negotiate further agreements planner. Within the framework of the development and implementation of the project can offer new ideas and / or needs. Dis mandates is therefore entitled to change the working results of the Consultant accordingly and / or be modified by third parties. Also reserves the mandates be extended, in the from / to the officer worked for the zone or call in by / the delegate object processed / project for the further planning and execution of other planners and / or employer. The Consultant expressly acknowledges the mandates all the necessary copyright powers.

Price: The agreed services to be present at a flat fee (no inflation adjustment) by CHF - gotten off ex VAT per multi-family house, which is operated by the commissioner. deducted from the fee already paid for the definition of interfaces to the podium.

If 60% of apartments sold the affected multi-family house, The Consultant will also receive a bonus payment of CHF --. 4D4-detached houses. 1/4d4.2 and 4d5.1/4d5.2 are ever as a family house, house is 4D3 than two apartment buildings. lm above flat fee includes the incorporation of the Interface Control Document (Static earthquake ,..." stairs / lift, building technology, building physics, etc.) is the / the agent is, moreover, an additional fee of inclusive CHF -.. excl VAT per edited by him multiple dwelling for the preparation

* Check all that apply and add if necessaryDate and signature symbol of the Parties

13 ****** . © sia / dg – informatik 1002-2003 No. 2387

Page 14: Zutreffendes ankreuzen und wenn nötig ergänzen

Sequel to "14 Special arrangements"

and revisions of notarial documents for land records. The inferiority linked to these plans must be submitted at a scale of 1:50.

The Andermatt Swiss Alps AG is finally an option right at all times to release the part performance "quote" too. This power is at a flat fee of CHF 10'000 - compensated ex VAT for each of the officers worked on multi-family house, the apartment house 4D3 as e is in an apartment building.

The above fees will be phased carefully. The Consultant is entitled to payments on account in the amount of up to 90% of the services provided.

This contract is issued and signed in 3 copies.

Place and date: Place and date:

For the Consultant For the Client

Andermatt Swiss Alps SA

Annex Dated and signed statement from Regulation SIA 102 (2003) for services and fees of architects (Article 1)

Supplement Schedule

Dated and signed on both sides Inserts *

1 * dates and deadlines

2 project organization (involved in the project partners and their contractual relationships)

3 provisions for data exchange and backup

4 personnel qualification table with categories and hourly rates at the time of the contract

5 payment schedule

6 fee calculation of construction costs

7

8

9

10

* Check all that apply and add if necessary

14 ****** . © sia / dg – informatik 1002-2003 No. 2387

Page 15: Zutreffendes ankreuzen und wenn nötig ergänzen

In the present text is the clarity of function names always chose the male form.The statements are in the same form of the function holders.

Article 1 General Conditions of Contract (Extract from Regulation SIA 102, 2003)1.1Applicable law and order

.1 For the legal relationship between the parties are critical:

- The completed contract- The present order, so far as it

is declared by the parties as applicable

- Swiss law.

.2Subject to the mandatory provisions of Swiss law, this order also prevail in the event of conflicting individual regulations.

1.2Conclusion of the contract

.1The contract is in writing, orally or completed by appropriate traNSACTION.

.2 The execution of a contract document and the written form of contract amendments are recommended. 1.3 Duties of the architect .1 Due Diligence The architect represents the interests of the client, in particular the attainment of its objectives, to the best knowledge and skills and providing the services contracted for in accordance with the generally recognized rules of his field. .2 Loyalty The architect takes from third parties such as contractors and suppliers, against any personal benefits. Knowledge of order processing, he kept confidential and not used to the detriment of the client. .3 Representing the client .31 Content and scope of powers of representation of architects, under the contract. .32 If in doubt, the architect of the instructions of the principal shall obtain for all legal business arrangements and to arrangements that are scheduled, either qualitatively or financially far. .33 From third parties such as public authorities, contractors, suppliers and other representatives, the architect represents the client legally binding if they are activities that are usually associated with the direct order fulfillment. All oral or written warnings are immediately forwarded in writing to the client. .34 To ward off harm and danger is the architect, in urgent cases without obtaining the consent of the contracting authority and obligation to take all appropriate measures or to order. .4 Official decrees Official orders, the negative decisions or restrictive requirements and conditions are included, the client immediately bring to the attention, there remains the possibility of seizure upheld by appeals. .5 Warning requirement .51 The architect is the client to follow his instructions, especially regarding deadlines, quality and cost, to our attention and to warn inappropriate orders and desire. The client persists in spite of warnings to its authority, is the architect for the consequences of not responsible. For the reminder of the written form is recommended. .52 The client persists in spite of warnings to not comply with safety rules, can the architect to also exclude its liability to third parties resign. Liability for damages to the client for unlawful dismissal, this is excluded. .6 Accountability At the request of the architect, each time on his administration accountable and publishes all the documents, their development, he has undertaken as part of the remuneration agreed by contract. .7 Document retention The work results remain the property of the architect. They are the originals or in some other appropriate, usable form for ten years from the completion of the order be kept.

15 ****** . © sia / dg – informatik 1002-2003 No. 2387

Page 16: Zutreffendes ankreuzen und wenn nötig ergänzen

1.4 Rights of the architect .1 Copyright The copyright of his work remains with the architects. When plants are in particular the designs and parts of plants, provided they are intellectual creations of individual character. .2 Publications The architect can publish his work while protecting the interests of the client. He is also the right to be mentioned in the publications of the client or third party as the author. .3 Involvement of third parties to fulfill the contract The architect is empowered to call in to meet his contractual obligations at their own expense a third party. .4 Payments, ensuring advance The architect is entitled to payments of at least 90% of the work performed under the contract. With the arrival of the final settlement with the client, the remaining fee for the services provided for the payment is due. The payment of the fee for the management, organization and monitoring of corrective action after the expiry of the Garantiefreist (notice period) according to SIA 118 (order) payable if the architect has provided the incumbent services. The architect may require secure the appropriate fee or deposit. Date and signature symbol of the Parties 14 1.5 Duties of the principal .1 Payment Invoices are payable within thirty days of receipt. The fee should correspond to the service provided. The full agreed fee is provided only for the contractual services owed. .2 Transfers Third parties the customer does not direct orders. Otherwise, he has guided the architects to time in writing. .3 Payments to third parties which The client is the architect of all time written note if payments made directly to third parties. .4 Loss prevention and mitigation The client shall take all reasonable measures in good time, which are effective in reducing the formation or enlargement of damage. He rises to one or more contractors or suppliers directly exceptionally complaints, it shall notify the architect in writing immediately. 1.6 Rights of the client .1 Transfers The client is entitled to instructions on the architect. The client insists on a transfer despite warnings, he alone bears the consequences. .2 Payments to third parties which In case of payment difficulties of the architect as well as for important reasons the client is entitled to pay an enlisted by the architect third parties (Article 1.4.3) with the effect against the architects directly. He hears this, prior to the parties. .3 Copies of work results The client is entitled to the work results, to their preparation has been the architect obliged to leave, make copies. He has to replace the architect the corresponding expenses. .4 Use of work results of the architect With the payment of the fee, the client is entitled to use the results of work of the architect for the agreed purpose. 1.7 Overall management The tasks of general management are described in Article 3.4.1 of this order. 1.8 Extensions and postponements Provides a party an agreed performance is not delivered on time, it can be set by the other party a written reminder. For the warning party to shift the terms and dates, has to respect it committed, is appropriate. Further claims remain reserved for delay.

16 ****** . © sia / dg – informatik 1002-2003 No. 2387

Page 17: Zutreffendes ankreuzen und wenn nötig ergänzen

1.9 Liability .1 Liability of Architects .11 With debt of incorrect order fulfillment, the architect has to compensate the client for the resulting damage. This is particularly true in breach of his fiduciary duty Sorgfaltsund, if ignored or violation of recognized rules in its field, with a lack of coordination or oversight, incomplete coverage and costs for failure to meet agreed deadlines or dates binding. .12 Where the achievement of the objectives of the customer depends on circumstances, to represent not the architect, he may not be non-attainment of a goal of the client as a result of these circumstances attributed to him. This is particularly true for the foreseeable uncertain decisions by third parties, such as on the issue of permits or credits. .13 Enlisted the services of independent third parties who are in direct contractual relationship with the client, the architect is not liable. .14 For the activities of third parties that he himself brought in the architect liable under Article 101 ¹ of Obligations. .15 If the customer requires a warning against the involvement of the architects of a particular third party, the architect is only responsible for proper instruction and supervision of the third. .2 Liability of the Customer for failure to meet deadlines and dates so far as it lies on the principal that time limits and deadlines are not met, he has to pay the architect any additional expenses. In addition, reserve the right to compensation claims of the architect. .3 Interruption of employment .31 In vorausgesehenem or not, in its length an uncertain interruption or significant delay of order handling, the architect is entitled to compensation for the damage it has incurred, if the principal in the interruption or delay in debt. .32 If, however, IMPOSE FINES the client after a planning phase with the commencement of the next phase, he owes the architect why no redress. .33 Caused the delay in resumption of work is additional services to their reward before the resumption of the work to be agreed in writing. Article 101 OR Liability for assistants ¹ If the discharge of a debt obligation or the exercise of a right arising from an obligation, even if the power legally, can be carried out by an assistant, such as household or employee, has to compensate the other hand the damage done by the assistant in the exercise of their functions. ² This liability may be made in advance by an agreement limited or excluded. ³ If, however, the waiver of the other end of the service or follows the liability from the operation of an authoritarian licensed trade, they shall be excluded the liability for no more than slight negligence. Date and signature symbol of the Parties 15 1:10 VAT VAT is included in the contract and all statements disclosed openly. It is paid in addition to that at the time of service delivery to the current set of fees, charges and fees of third-party services agreed by the client. 1:11 Limitation .1 General limitation Claims under the contract expire within ten years from the date of the injurious act. .2 In factory defects .21 Claims arising from defects in the building expire within five years. The period begins with the acceptance of the work or part of the plant to run. Such defects can be reported during the first two years after the purchase at any time. After this period, the defects are immediately reported after the discovery. , Resulting from the delayed damage complaint with the principal himself. .22 In advisory opinions, the limitation period is calculated in accordance with the Swiss Code of Obligations. 1:12

17 ****** . © sia / dg – informatik 1002-2003 No. 2387

Page 18: Zutreffendes ankreuzen und wenn nötig ergänzen

Early termination of the contract 1 The legal consequences of early termination of the contract shall be governed by the provisions of the Swiss Code of Obligations. .2 If the termination by the client at the wrong time, so the architect is entitled to demand in addition to his fee for the work done under contract, a surcharge. The surcharge is 10% of the fee for the confiscated order part or more, if the detected damage is greater. An unlawful dismissal by the client exists in particular if the architect was no reasonable cause for termination and the termination in the timing and the dispositions made by him adversely to him. .3 If the notice is given by the architects at the wrong time, the client is entitled to compensation for proven loss. 1:13 Mediation Unless agreed in writing, concerning any agreement emerging from the resulting disputes (including those of the valid conclusion of the contract, the validity, amendment or repeal) to conduct a mediation process. 1:14 Jurisdiction .1 Responsible for the assessment of disputes among the parties to the ordinary courts. .2 However, if agreed in writing, such disputes by arbitration in accordance with Directive SIA 150 (Directive to proceedings before an arbitration court) decided.

18 ****** . © sia / dg – informatik 1002-2003 No. 2387

Page 19: Zutreffendes ankreuzen und wenn nötig ergänzen

X Projektorganisation (am Projekt beteiligte Partner und ihre vertraglichen Beziehungen)

X Bestimmungen zum Datenaustausch und zur Datensicherung

Personaltabelle mit Qualifikationskategorien und Stundenansätzen zur Zeit des Vertragsabschlusses Zahlungsplan X Honorarberechnung nach Baukosten

Datum und Unterschriftenkürzel der Vertragsparteien

13

Im vorliegenden Text ist der Übersichtlichkeit halber für Funktionsbezeichnungen immer die männliche Form gewählt. Die Aussagen gelten in gleicher Form auch für Funktionsträgerinnen.

Art. 1 Allgemeine Vertragsbedingungen (Auszug aus Ordnung SIA 102, 2003)

1.1

Anwendbares Recht und Rangordnung

.1

Für das Rechtverhältnis zwischen den Vertragsparteien sind massgebend:

- der abgeschlossene Vertrag

- die vorliegende Ordnung, soweit sie von den Parteien als anwendbar erklärt wird

- das schweizerische Recht.

.2

Vorbehältlich der zwingenden Bestimmungen des schweizerischen Rechts ist diese Reihenfolge auch massgebend für den Fall, dass sich einzelne Bestimmungen widersprechen sollten.

1.2

Abschluss des Vertrages

.1

Der Vertrag wird schriftlich, mündlich oder durch entsprechendes Handels abgeschlossen.

.2

Die Ausfertigung einer Vertragsurkunde und die Schriftlichkeit von Vertragsänderungen werden empfohlen.

1.3

Pflichten des Architekten

.1

Sorgfaltspflicht

Der Architekt wahrt die Interessen des Auftraggebers, insbesondere die Erreichung seiner Ziele, nach bestem Wissen und Können und erbringt die vertraglich vereinbarten Leistungen unter Beachtung der allgemein anerkannten Regeln seines Fachgebiets.

.2

Treuepflicht

Der Architekt nimmt von Dritten, wie Unternehmern und Lieferanten, keine persönlichen Vergünstigungen entgegen. Kenntnisse aus der Auftragsbearbeitung behandelt er vertraulich und verwendet sie nicht zum Nachteil des Auftraggebers.

.3

Vertretung des Auftraggebers

.31

19 ****** . © sia / dg – informatik 1002-2003 No. 2387

Page 20: Zutreffendes ankreuzen und wenn nötig ergänzen

Inhalt und Umfang der Vertretungsbefugnisse des Architekten richten sich nach dem Vertrag.

.32

Im Zweifelsfall hat der Architekt die Weisungen des Auftraggebers einzuholen für alle rechtsgeschäftlichen Vorkehren sowie für Anordnungen, die terminlich, qualitativ oder finanziell wesentlich sind.

.33

Gegenüber Dritten, wie Behörden, Unternehmern, Lieferanten und weiteren Beauftragten, vertritt der Architekt den Auftraggeber rechtsverbindlich, soweit es sich um Tätigkeiten handelt, die mit der Auftragserledigung üblicherweise direct zusammenhängen. Sämtliche mündlichen oder schriftlichen Abmahnungen sind umgehend in schriftlicher Form an den Auftraggeber weiterzuleiten.

.34

Zur Abwehr von Schaden und Gefahr ist der Architekt, in dringlichen Fällen auch ohne Einholung des Einverständnisses des Auftraggebers, befugt und verpflichtet, sämtliche angemessenen Massnahmen zu ergreifen bzw. anzuordnen.

.4

Behördliche Verfügungen

Behördliche Verfügungen, die negative Entscheide oder einschränkende Auflagen und Bedingungen enthalten, sind dem Auftraggeber sofort zur Kenntnis zu bringen, so dass die Möglichkeit zur Ergreifung von Rechtsmitteln gewahrt bleibt.

.5

Abmahnungspflicht

.51

Der Architekt hat den Auftraggeber auf Folgen seiner Weisungen, insbesondere hinsichtlich Terminen, Qualität und Kosten, aufmerksam zu machen und unzweckmässige Anordnungen und Begehren abzumahnen. Beharrt der Auftraggeber trotz Abmahnung auf seiner Weisung, ist der Architekt für deren Folgen nicht verantwortlich.

Für die Abmahnung wird die Schriftform empfohlen.

.52

Beharrt der Auftraggeber trotz Abmahnung darauf, Sicherheitsregeln nicht einzuhalten, kann der Architekt, um seine Haftung auch gegenüber Dritten auszuschliessen, sein Mandat niederlegen. Eine Schadenersatzpflicht gegenüber dem Auftraggeber wegen Kündigung zur Unzeit ist diesfalls ausgeschlossen.

.6

Rechenschaftsablegung

Auf Verlangen legt der Architekt jederzeit über seine Geschäftsführung Rechenschaft ab und gibt alle Unterlagen heraus, zu deren Erstellung er sich im Rahmen der vereinbarten Honorierung vertraglich verpflichtet hat.

.7

Aufbewahrung von Dokumenten

Die Arbeitsergebnisse bleiben Eigentum des Architekten. Sie sind als Originale oder in geeigneter anderer, gebrauchsfähiger Form während zehn Jahren ab Beendigung des Auftrages aufzubewahren.

1.4

Rechte des Architekten

.1

Urheberrecht

Das Urheberrecht an seinem Werk verbleibt beim Architekten. Als Werke gelten insbesondere auch Entwürfe und Teile von Werken, sofern es sich um geistige Schöpfungen mit individuellem Charakter handelt.

.2

Veröffentlichungen

Der Architekt kann sein Werk unter Wahrung der Interessen des Auftraggebers veröffentlichen. Es steht ihm auch das Recht zu, in entsprechenden Veröffentlichungen des Auftraggebers oder Dritter als Urheber genannt zu werden.

20 ****** . © sia / dg – informatik 1002-2003 No. 2387

Page 21: Zutreffendes ankreuzen und wenn nötig ergänzen

.3

Beizug von Dritten zur Vertragserfüllung

Der Architekt ist befugt, für die Erfüllung seiner vertraglichen Pflichten, auf eigene Kosten Dritte beizuziehen.

.4

Abschlagszahlungen, Sicherstellung, Vorauszahlung

Der Architekt hat Anspruch auf Abschlagszahlungen von mindestens 90% der vertragsgemäss erbrachten Leistungen. Mit Eintreffen der Schlussabrechnung beim Auftraggeber wird das restliche Honorar für die erbrachten Leistungen zur Zahlung fällig. Die Zahlung des Honorars für die Leitung, Organisation und Überwachung der Mängelbehebung wird nach Ablauf der Garantiefreist (Rügefrist) gemäss Norm SIA 118 (Ordnung) fällig, wenn der Architekt die ihm obliegenden Leistungen erbracht hat.

Der Architekt kann Sicherstellung seines Honorars oder angemessene Vorauszahlung verlangen.

Datum und Unterschriftenkürzel der Vertragsparteien

14

1.5

Pflichten des Auftraggebers

.1

Zahlungsbedingungen

Die Rechnungen sind innerhalb von dreissig Tagen nach Erhalt zu begleichen. Das Honorar soll der erbrachten Leistung entsprechen. Das volle vereinbarte Honorar ist nur für die vertragsgemäss erbrachte Leistung geschuldet.

.2

Weisungen

Dritten erteilt der Auftraggeber keine direkten Weisungen. Andernfalls hat er den Architekten rechtzeitig schriftlich zu orientieren.

.3

Zahlungen an beigezogene Dritte

Der Auftraggeber gibt dem Architekten rechtzeitig schriftlich Kenntnis von allenfalls direkt an Dritte geleistete Zahlungen.

.4

Schadenverhütung und -minderung

Der Auftraggeber ergreift rechtzeitig alle zumutbaren Massnahmen, die geeignet sind, der Entstehung oder Vergrösserung eines Schadens entgegenzuwirken. Erhebt er gegenüber einem oder mehreren Unternehmern oder Lieferanten ausnahmsweise direkt Mängelrügen, so teilt er dies dem Architekten unverzüglich schriftlich mit.

1.6

Rechte des Auftraggebers

.1

Weisungen

Der Auftraggeber ist gegenüber dem Architekten weisungsberechtigt. Beharrt der Auftraggeber trotz Abmahnung auf einer Weisung, so trägt er allein die Folgen.

.2

Zahlungen an beigezogene Dritte

Bei Zahlungsschwierigkeiten des Architekten sowie bei Vorliegen wichtiger Gründe ist der Auftraggeber berechtigt, einen durch den Architekten beigezogenen Dritten (Art. 1.4.3) mit befreiender Wirkung gegenüber dem Architekten direkt zu bezahlen. Er hört jedoch hierzu vorgängig die Beteiligten an.

.3

Kopien von Arbeitsergebnissen

21 ****** . © sia / dg – informatik 1002-2003 No. 2387

Page 22: Zutreffendes ankreuzen und wenn nötig ergänzen

Der Auftraggeber ist berechtigt, von den Arbeitsergebnissen, zu deren Herstellung sich der Architekt verpflichtet hat, Kopien erstellen zu lassen. Er hat dem Architekten die entsprechenden Auslagen zu ersetzen.

.4

Nutzung von Arbeitsergebnissen des Architekten

Mit Bezahlung des Honorars steht dem Auftraggeber das Recht zu, die Arbeitsergebnisse des Architekten für den vereinbarten Zweck zu verwenden.

1.7

Gesamtleitung

Die Aufgaben der Gesamtleitung sind in Art. 3.4.1 dieser Ordnung umschrieben.

1.8

Fristverlängerungen und Terminverschiebungen

Erbringt eine Partei eine vereinbarte Leistung nicht fristgemäss, kann sie von der anderen Partei durch schriftliche Mahnung in Verzug gesetzt werden. Für die mahnende Partei verschieben sich die Fristen und Termine, zu deren Einhaltung sie sich verpflichtet hat, angemessen. Weitere Ansprüche aus Verzug bleiben vorbehalten.

1.9

Haftung

.1

Haftung des Architekten

.11

Bei verschuldet fehlerhafter Auftragserfüllung hat der Architekt dem Auftraggeber den dadurch entstandenen Schaden zu ersetzen. Dies gilt insbesondere bei Verletzung seiner Sorgfaltsund Treuepflicht, bei Nichtbeachtung oder Verletzung anerkannter Regeln seines Fachgebietes, bei mangelnder Koordination oder Beaufsichtigung, bei ungenügender Kostenerfassung sowie bei Nichteinhaltung von verbindlich vereinbarten Fristen oder Terminen.

.12

Wo die Erreichung der Ziele des Auftraggebers von Umständen abhängt, die nicht der Architekt zu vertreten hat, kann ihm das Nicht-Erreichen eines Ziels des Auftraggebers infolge dieser Umstände nicht zur Last gelegt werden. Dies gilt insbesondere auch für die nicht sicher voraussehbaren Entscheide von Dritten, etwa betreffend die Erteilung von Bewilligungen oder Krediten.

.13

Für die Leistungen von beigezogenen selbständigen Dritten, die im direkten Vertragsverhältnis zum Auftraggeber stehen, haftet der Architekt nicht.

.14

Für die Tätigkeiten von Dritten, die er selber beigezogen hat, haftet der Architekt gemäss Art. 101 Obligationenrecht¹.

.15

Verlangt der Auftraggeber entgegen der Abmahnung des Architekten den Beizug eines bestimmten Dritten, haftet der Architekt lediglich für gehörige Instruktion und Überwachung des Dritten.

.2

Haftung des Auftraggebers bei Nichteinhaltung von Fristen und Terminen Soweit es am Auftraggeber liegt, dass Fristen und Termine nicht eingehalten werden, hat er dem Architekten allfällige Mehraufwendungen zu vergüten. Darüber hinausgehende Schadenersatzansprüche des Architekten bleiben vorbehalten.

.3

Arbeitsunterbruch

.31

Bei nicht vorausgesehenem oder in seiner Länge ungewissem Unterbruch oder bei erheblicher Verzögerung der Auftragserledigung hat der Architekt Anspruch auf Ersatz des ihm erwachsenen Schadens, falls der Auftraggeber den Unterbruch bzw. die Verzögerung verschuldet hat.

22 ****** . © sia / dg – informatik 1002-2003 No. 2387

Page 23: Zutreffendes ankreuzen und wenn nötig ergänzen

.32

Verlangt jedoch der Auftraggeber nach Abschluss einer Planungsphase mit der Inangriffnahme der nächsten Phase zuzuwarten, so schuldet er deswegen dem Architekten keinen Schadenersatz.

.33

Bedingt die Verzögerung bei Wiederaufnahme der Arbeiten zusätzliche Leistungen, ist deren Honorierung vor der Wiederaufnahme der Arbeiten schriftlich zu vereinbaren.

Art. 101 OR

Haftung für Hilfspersonen

¹ Wer die Erfüllung einer Schuldpflicht oder die Ausübung eines Rechtes aus einem Schuldverhältnis, wenn auch befugterweise, durch eine Hilfsperson, wie Hausgenossen oder Arbeitnehmer, vornehmen lässt, hat dem anderen den Schaden zu ersetzen, den die Hilfsperson in Ausübung ihrer Verrichtungen verursacht.

² Diese Haftung kann durch eine zum Voraus getroffene Verabredung beschränkt oder aufgehoben werden.

³ Steht aber der Verzichtende im Dienst des anderen oder folgt die Verantwortlichkeit aus dem Betriebe eines obrigkeitlich konzessionierten Gewerbes, so darf die Haftung höchstens für leichtes Verschulden wegbedungen werden.

Datum und Unterschriftenkürzel der Vertragsparteien

15

1.10

Mehrwertsteuer

Die Mehrwertsteuer ist im Vertrag und in allen Abrechnungen offen auszuweisen. Sie ist zu dem im Zeitpunkt der Leistungserbringung aktuellen Satz zusätzlich zu den Honoraren, Nebenkosten und vereinbarten Vergütungen von Drittleistungen durch den Auftraggeber zu bezahlen.

1.11

Verjährung

.1

Generelle Verjährung

Ansprüche aus dem Vertrag verjähren innert zehn Jahren ab dem Zeitpunkt der schädigenden Handlung.

.2

Bei Werkmängeln

.21

Ansprüche aus Mängeln des Bauwerkes verjähren innert fünf Jahren. Die Frist beginnt mit der Abnahme des Werkes beziehungsweise des Werkteils zu laufen. Solche Mängel können während der ersten zwei Jahre nach der Abnahme jederzeit gerügt werden. Nach Ablauf dieser Frist sind die Mängel sofort nach der Entdeckung zu rügen. Den aus der verzögerten Rüge entstehenden Schaden trägt der Auftraggeber selber.

.22

Bei Gutachten bemisst sich die Verjährungsfrist nach Massgabe des Schweizerischen Obligationenrechtes.

1.12

Vorzeitige Beendigung des Vertrages

1

Die Rechtsfolgen einer vorzeitigen Beendigung des Vertrages richten sich nach den Bestimmungen des Schweizerischen Obligationenrechts.

.2

Erfolgt die Kündigung durch den Auftraggeber zur Unzeit, so ist der Architekt berechtigt, nebst seinem Honorar für die vertragsgemäss geleistete Arbeit, einen Zuschlag zu fordern. Der Zuschlag beträgt 10% des Honorars für den entzogenen Auftragsteil oder mehr, wenn der nachgewiesene Schaden grösser ist. Eine Kündigung zur Unzeit durch den Auftraggeber liegt insbesondere vor, wenn der Architekt

23 ****** . © sia / dg – informatik 1002-2003 No. 2387

Page 24: Zutreffendes ankreuzen und wenn nötig ergänzen

keinen begründeten Anlass zur Kündigung gegeben hat und die Kündigung hinsichtlich des Zeitpunktes und der von ihm getroffenen Dispositionen für ihn nachteilig ist.

.3

Erfolgt die Kündigung durch den Architekten zur Unzeit, hat der Auftraggeber Anspruch auf Ersatz des nachgewiesenen Schadens.

1.13

Mediation

Sofern schriftlich vereinbart, ist über allfällige sich aus dem vorliegenden Vertrag ergebende Streitigkeiten (einschliesslich solche über das gültige Zustandekommen des Vertrages, dessen Rechtswirksamkeit, Abänderung oder Aufhebung) ein Mediationsverfahren durchzuführen.

1.14

Gerichtsbarkeit

.1

Zuständig für die Beurteilung von Streitigkeiten unter den Vertragsparteien sind die ordentlichen Gerichte.

.2

Sofern aber schriftlich vereinbart, werden solche Streitigkeiten durch ein Schiedsgericht gemäss Richtlinie SIA 150 (Richtlinie

für das Verfahren vor einem Schiedsgericht) entschieden.

24 ****** . © sia / dg – informatik 1002-2003 No. 2387